PSNC (Poland): Zuzanna Scigacz, Marcin Ptociennik CSIC (Spain): Emilio Diaz. CNIT (Italy): Davide Adami ELETTRA (Italy): Alessio Curri EUCENTRE (Italy): Matteo Lanati OGS (Italy): Giorgio Bolzon ECHOHYDROS (Spain): GRNET (Greece): Ioannis Liabotis UC (Spain):
1. Deliverable DSA2.4
a. TOC b. Contributions c. Delivery Date
2. Usage of the production e-Infrastructure
3. Organization of periodic SA2 meeting until the end of the project.
Discussion started by presenting the TOC of DSA2.4
This deliverable has to be ready for submission on the 1st February.
Final draft from SA2 has to be sent to the list by 14th of January and contributions from partners in placeholders of the deliverable to be sent to Ioannis by the 19th of January.
Deliverable to be sent for internal review at the 22nd of January.
In the meantime Ioannis to send e-mails for contributions that can come earlier.
Action points related to the deliverable:
1. ALL to check the contents of the deliverable and correct add information relevant to their work. This is mainly for Sections 2 and 3 of the deliverable.
2. ELETTRA, ALL, to explain where each instrument is located after a list is sent by Ioannis
3. PSNS, to send information about the installation of GPU resources in the infrastructure, Ioannis to remind
4. ELETTRA, Milan, to correct the middleware deployment part
5. ELETTRA, to provide information on the usage of the gridats VO, after the 1st version is sent to the list.
6. ELETTRA to provide information on the usage of NAGIO in ELETTRA site and also provide availability data from Nagios.
7. GRNET, ELETTRA discuss IE accounting issues
8. GRNET, Ioannis to send the queries for accounting to all.
Action Points
1. Monthly Statistics to be produced at each SA2 teleconference
2. GRNET, Ioannis to ask NA3 why there is not production usage of the infrastructure and identify if there is a problem in the infrastructure.
Monthly teleconferences to be scheduled one week in advance targeting at the 1st week of the month.